Riviera Maya, Q.R. — Environmental inspectors have fined several companies for irregular construction along the coast. Federal inspectors say fines were handed out after they found environmental damage to mangrove vegetation.

The damage was located in Laguna Nichupté, Isla Holbox, and Puerto Morelos due to illegal construction and modifications to the state’s coastline.

The Federal Attorney General for Environmental Protection (Profepa) reported conducting inspection from October 26 to November 4 in the municipalities of Benito Juárez, Lázaro Cárdenas and Puerto Morelos.

During the inspections, they found damage to mangrove vegetation due to the construction of a pier and real estate works, as well as modifications to the coastline and occupation of a beach area with tourist furniture.

“As a result of the investigations, a 1,195.346 m² pier under construction was identified in the Nichupté Lagoon with direct impact on the mangrove,” they reported.

They also reported finding “a five-story building and associated works for a swimming pool occupying 667 m² on Holbox Island and the presence of palapas, sun loungers, wooden structures, kayaks, tables, and a lifeguard lookout on a beach in Puerto Morelos where modifications to the coastline configuration were also observed.”

Due to the lack of accreditation of federal environmental impact authorizations, Profepa imposed a safety measure consisting of the total temporary closure of the pier construction in Laguna Nichupté and the five-story building and associated swimming pool works on Isla Holbox.

In Puerto Morelos, a detailed report was drawn up to document the beach conditions and the occupation of the Federal Maritime Terrestrial Zone (Zofemat).

In Laguna Nichupté, during the inspection on October 26 in the Cancun Hotel Zone, “the construction of a T-shaped pier with side platforms was reviewed. It occupies 1,195.346 m² within a total inspected area of 8,766 m². Direct impact on mangrove vegetation was observed at the site,” they detailed.

On October 28th, an inspection was carried out on a property on Caguama Street on Holbox Island. A five-story building, a concrete slab, and structural preparations for a swimming pool were found. The construction occupies 667 m² of a 982 m² plot of land.

On November 4th in Puerto Morelos, in front of the Breathless Hotel, a Zofemat (Federal Maritime Land Zone) boundary was inspected. During the inspection, it was observed that the coastline has been altered and that the originally delimited boundary now merges with the marine waters. The presence of tourist furniture and equipment on the adjacent beach was also documented.

Profepa (Procuraduría Federal de Protección al Ambiente) will follow up on the corresponding administrative procedures for the inspected projects in Laguna Nichupté and Isla Holbox.

It will also assess the damage to the mangroves to determine corrective measures and, where applicable, appropriate ecological restoration actions.

In the case of Puerto Morelos, it will carry out the technical analysis of the Zofemat delimitation, considering the modifications observed in the coastline, in order to determine the legal status of the furniture and tourist equipment installed on the beach.

Mangroves and coastal dunes perform essential environmental functions, protecting coastlines from weather events, capturing carbon, and providing refuge for numerous species of flora and fauna.

Therefore, any projects or activities that may affect these ecosystems must, where applicable, have prior environmental impact authorization issued by the Ministry of Environment and Natural Resources (Semarnat).

Profepa says they will continue with inspection and surveillance actions to verify compliance with environmental legislation and determine the corresponding responsibilities and measures.