Puerto Morelos, Q.R. — Mayor Blanca Merari Tziu Muñoz says progress is being made in the 18 planned projects for Puerto Morelos this year. According to Merari, nine of those planned projects have been finished.

Merari reported that three street construction and paving projects in Leona Vicario are over 95% complete, while the remaining six projects are still in progress, representing an overall physical progress of more than 73%.
The mayor stressed the importance of maintaining constant oversight of the work and reviewing both its progress and the budget execution in order to ensure that public investment translates into infrastructure that meets the needs of the families of Puerto Morelos.
“We are closely monitoring each of the priority projects. Currently, we have a contracted investment of 81,022,718 pesos. Of that amount, 53,596,094 pesos correspond to projects that are 100% complete, while 27,426,624 pesos correspond to the nine projects that are still underway.
Our commitment is that every resource translates into results and well-being for the families of Puerto Morelos,” stated Blanca Merari.
Mario Salinas Castro, the Secretary of Public Works, said that the project resources come from different sources including the Puerto Morelos Environmental Sanitation Right Investment and Administration Trust (FIADSA), the Municipal Strengthening Contribution Fund (FORTAMUN), the Municipal Social Infrastructure Contribution Fund (FAISMUN), as well as Fiscal Resources.
He explained among the nine completed projects are the second stage of rehabilitation of the fishing pier, the first stage of lighting on Federal Highway 307, the reconstruction of the access road to Bahía Petempich, the construction of Propela Street and 5th and 6th Streets in the Tierra Nueva neighborhood and the maintenance of wells in Puerto Morelos and Leona Vicario.
Completed is also the rehabilitation of Propela Street in the section from Vallarta to Galeón and the construction of safe crossings in school zones.

Meanwhile, the construction of Nauyaca Street (between Federal Highway 180 Mérida to Puerto Juárez and Cascabel Street) is 95% complete, as is the paving of Ignacio Ruiz Davis Street (between Apolinar Reyes Street and Benito Juárez Street) and Apolinar Reyes Street (between Ignacio Ruiz Davis Street and Hacienda Santa María Street).
Construction of the median on Timón Avenue, from Vallarta Street to 37th Street, is more than 80% complete, he reported.
The remaining projects include the first stage of the new Animal Welfare Center in Puerto Morelos, the rehabilitation of the Isaac Hamui Sports Unit, paving of Remolino Street (between Federal Highway 180 Merida to Puerto Juarez and Cielo Street), paving of Tierra Street (between Tina Street and Remolino Street) and paving of Cielo Street.

The mayor reiterated that reviewing physical and financial progress allows for maintaining control of investment, monitoring construction commitments, and ensuring that projects are developed according to schedule and with complete transparency.