SICT provides progress reports on City of Cancun road projects

Cancun, Q.R. — The City of Cancun says their road projects are on schedule after a report by the Secretariat of Infrastructure, Communications and Transportation (SICT).

According to the SICT, the remodeling of Luis Donaldo Colosio Boulevard is approximately 18 percent complete. Their progress report says they are currently working on the fifth section of the Playa del Carmen-Cancun road between Plaza La Roca and Colegio St. Johns.

In addition, the construction of the airport junction is just over 15 percent advanced. The SICT says they are working on the excavation for the foundation of the central support of the new structure.

Construction of the Nichupté Vehicular Bridge over the lagoon to connect the Cancun Hotel Zone with the mainland is also a current project the SICT says is only six percent advanced. The agency says they are currently carrying out the first stages of work at the intersection of Av. Kabah with Tulum and Bonampak.